Industry field guide
Multifamily punch list and closeout records for AI
Two apartments can have the same room labels and different punch lists.
- Sector
- Construction
- 2022 NAICS
- 236116
- Practice pack
- Example and answer key (JSON)
- Updated
What this guide tests
Which kitchen item has a verified closeout, and should the duplicate photo close the similarly named Building B item?
See the specimen and fields · Work through the fictional records
Task and source context
Two apartments can have the same room labels and different punch lists. A construction assistant needs the building, floor and unit before attributing a closeout photo. USACE’s construction quality materials show why staged reviews matter. Troveo publicly describes construction project records as a possible data source. USACE Construction Quality Management · Troveo construction data guide
Create a mock corridor with two units. Give one item a verified recheck and attach a visually similar photo from another unit to the second. Ask which item was closed and which needs an authorized reviewer. Keep the initial observation, assignment, photo and follow-up status in separate fields.
Use owned props and fictional floor or unit labels. Exclude actual property layouts, future occupants, worker identities, commercial records, and third-party images that are not cleared.
Industry research
The U.S. Census Bureau’s industry definitions establish which activities these codes cover. The workflow sources in this guide describe the task or record type. Fiund’s pilot below uses fictional material to test a specific decision within that scope.
236116 · New Multifamily Housing Construction (except For-Sale Builders)
This U.S. industry comprises general contractor establishments primarily responsible for the construction of new multifamily residential housing units (e.g., high-rise, garden, town house apartments, and condominiums where each unit is not separated from its neighbors by a ground-to-roof wall). Multifamily design-build firms and multifamily housing construction management firms acting as general contractors are included in this industry.
Build a pilot sample
Set up this pilot
Use two mock kitchens with the same punch-list wording. Link a before-and-after photo to one unit and require unit-specific reviewer confirmation to close it.
Prepare the test packets
- Start with the worked case. Use the fictional record types below as a guide to the source files you need. Give each packet a stable ID and save its source versions with it.
- Change one fact. Make one packet with enough evidence to answer the question and one where the evidence points to a different answer. Keep the other fields fixed so a reviewer can tell what changed.
- Remove the decisive evidence. Give the reviewer a third packet with a plausible near-match in its place. Have them write what can still be established and what evidence would resolve the rest.
Fields the reviewer needs
- Building, floor, unit and item key
- Creates an unambiguous work-item identity.
- Photo identity and visible card
- Detects a copied or misfiled attachment.
- Reviewer and closeout state
- Separates an image upload from an authorized recheck.
Use How construction and trade teams can contribute data for AI to turn the specimen into a brief with a defined task, source and review owner.
Fictional exercise
A closeout photo needs a full unit identity
A synthetic multifamily punch list contains two identically named kitchens. Fictional building, floor and unit labels distinguish the work items.
| Record ID | Source | What it records |
|---|---|---|
| MP1 | Original punch register | Building A, floor 2, unit 201: kitchen item K1 open. Building B, floor 2, unit 201: kitchen item K1 open. |
| MP2 | Reviewed closeout | Building A / 2 / 201 / K1 rechecked and marked complete, with photo A-7. |
| MP3 | Misfiled attachment | Building B's K1 folder contains photo A-7. Its visible card reads Building A. No Building B recheck is supplied. |
Question for the model. Which kitchen item has a verified closeout, and should the duplicate photo close the similarly named Building B item?
Show the reference answer
MP2 verifies closeout for Building A, floor 2, unit 201, item K1. MP3 is the same A-7 image filed in Building B's folder, with a visible Building A card. It supplies no independent Building B evidence. Keep Building B's item open under MP1 and flag the attachment conflict. Repeated room, unit and item names cannot replace the full building-specific identity.
How to check the result
Ask for the answer, the record IDs that support it and any fact the evidence leaves unresolved. Have a reviewer compare the response against the reference before deciding whether the sample is ready to expand.
Errors to flag in this case
- Joining the two items on unit 201 and kitchen K1 while dropping the building.
- Treating duplicate attachment placement as a second reviewed closeout.
Change the inputs and run it again
Add a Building B photograph with the correct card but no reviewer disposition. Score the image association as resolved while keeping authorized closeout pending.
Score the decision and the evidence separately
Save the reviewer’s expected answer, supporting record IDs and unresolved fields in a separate answer key. Score the model on the decision, its citations and its handling of the deliberate gap. A correct answer citing a different case counts as an evidence error.
Before expanding collection, have a second reviewer run the same checks on the held-out packet. Keep related versions, views and exports of the same case together so they stay on one side of the training and evaluation split.
Check permission and scope
Use invented floor labels and owned props. Exclude real apartment layouts, future occupants, worker identities and private property records.
Keep customer addresses, access codes and confidential drawings out of the test material. Obtain authorization for any identifiable site imagery.
Describe an authorized archive through Fiund’s existing-data assessment, or describe a new capture capability through the collection brief. The contributor agreement covers the terms for participation.
Sources and further reading
Resources for this workflow
Company and program reviews
Use these reviews to compare sourcing, capture or evaluation approaches. Confirm the applicable program, accepted sources and terms with the provider.
Provider cited in this guide
Troveo review: video licensing, business data and creator payouts
The guide cites material from this provider. The review explains the offering and which details require a specific brief or agreement.
Compare the approach
micro1 review for experts, trade footage and company data
Compare how a trade recording project differs from an expert role or a company data partnership.
Compare the approach
Scale AI review: data partnerships, Outlier and buyer services
Read the documented operational-data route for established field-service businesses.
Related industry examples
Industry guide · NAICS 236115
Custom home selection and installation records for AI
An owner can approve a window selection while the site packet still shows the prior opening.
Industry guide · NAICS 236210
Industrial building submittal and installation data for AI
A component can appear in a proposed substitution before it is authorized for installation.
Industry guide · NAICS 236220
Commercial building turnover records for AI review
A contractor can complete an item while the owner’s acceptance is still open.