An advisor can teach a model to distinguish variance against an original schedule from variance against an approved revision.
- 2022 NAICS
- 541611
- Practice pack
- Example and answer key (JSON)
- Updated
What this guide tests
What schedule variances are supported against the original and approved current baselines, and can the unsigned proposal make M early?
See the specimen and fields · Work through the fictional records
Task and source context
An advisor can teach a model to distinguish variance against an original schedule from variance against an approved revision. GAO publishes schedule assessment practices. Scale AI lists business and professional services in its program for real operational records. Confirm the current sourcing scope and who can authorize those records. GAO Schedule Assessment Guide · Scale Data Partnerships
Write a fictional project with a milestone planned for day 20, an approved baseline change to day 23 and actual completion on day 25. Include an unsigned proposal for day 26. Ask for the variance against each approved baseline and citations for each date.
Exclude real performance reviews, client plans, fees and staffing decisions. Use your own project records for the example and verify rights to every source if pursuing a real dataset.
Industry research
The U.S. Census Bureau’s industry definitions establish which activities these codes cover. The workflow sources in this guide describe the task or record type. Fiund’s pilot below uses fictional material to test a specific decision within that scope.
541611 · Administrative Management and General Management Consulting Services
This U.S. industry comprises establishments primarily engaged in providing operating advice and assistance to businesses and other organizations on administrative management issues, such as financial planning and budgeting, equity and asset management, records management, office planning, strategic and organizational planning, site selection, new business start-up, and business process improvement.
Build a pilot sample
Set up this pilot
Draw a mock baseline schedule, signed revision and unsigned proposal. Compute variance against both approved dates without allowing the draft to change the comparison.
Prepare the test packets
- Start with the worked case. Use the fictional record types below as a guide to the source files you need. Give each packet a stable ID and save its source versions with it.
- Change one fact. Make one packet with enough evidence to answer the question and one where the evidence points to a different answer. Keep the other fields fixed so a reviewer can tell what changed.
- Remove the decisive evidence. Give the reviewer a third packet with a plausible near-match in its place. Have them write what can still be established and what evidence would resolve the rest.
Fields the reviewer needs
- Milestone and baseline version
- Defines the comparison target.
- Approval and planned date
- Separates authorized revision from proposal.
- Actual completion source
- Makes each variance reproducible.
Use Build an AI evaluation from professional work to turn the specimen into a brief with a defined task, source and review owner.
Fictional exercise
Report variance against the original and approved revised baselines separately
An independently authored project timeline uses artificial milestone days. It contains no client performance review, staffing decision, fee or real project plan.
| Record ID | Source | What it records |
|---|---|---|
| MCB1 | Original practice baseline | Milestone M planned day 20. |
| MCB2 | Approved baseline revision B2 | M planned day 23, explicitly replacing the current baseline date while retaining B1 history. |
| MCB3 | Completion and draft | Actual M complete day 25. Unsigned proposal B3 suggests day 26; no approval. |
Question for the model. What schedule variances are supported against the original and approved current baselines, and can the unsigned proposal make M early?
Show the reference answer
MCB3's actual day 25 is five days after MCB1's original day 20 and two days after MCB2's approved revised day 23. Both comparisons are supported when their baseline labels are preserved. The day-26 proposal would make the arithmetic look early, but it lacks approval and is not the current baseline. Report the original and revised variances without selecting a convenient unapproved reference.
How to check the result
Ask for the answer, the record IDs that support it and any fact the evidence leaves unresolved. Have a reviewer compare the response against the reference before deciding whether the sample is ready to expand.
Errors to flag in this case
- Reporting a variance without naming which baseline it uses.
- Using an unsigned later proposal to recast a late milestone as early.
Change the inputs and run it again
Approve a revision affecting another milestone only. Require M's baseline to remain day 23 despite the newer project-file date.
Score the decision and the evidence separately
Save the reviewer’s expected answer, supporting record IDs and unresolved fields in a separate answer key. Score the model on the decision, its citations and its handling of the deliberate gap. A correct answer citing a different case counts as an evidence error.
Before expanding collection, have a second reviewer run the same checks on the held-out packet. Keep related versions, views and exports of the same case together so they stay on one side of the training and evaluation split.
Check permission and scope
Use original fictional timelines. Exclude client plans, fees, performance reviews and staffing records.
Use original or licensed practice material. Leave client work product, confidentiality obligations and regulated outcomes out of the sample.
Describe an authorized archive through Fiund’s existing-data assessment, or describe a new capture capability through the collection brief. The contributor agreement covers the terms for participation.
Sources and further reading
Resources for this workflow
Company and program reviews
Use these reviews to compare sourcing, capture or evaluation approaches. Confirm the applicable program, accepted sources and terms with the provider.
Provider cited in this guide
Scale AI review: data partnerships, Outlier and buyer services
The guide cites material from this provider. The review explains the offering and which details require a specific brief or agreement.
Compare the approach
Invisible Technologies review for expert-led AI training
Compare expert calibration and reviewer agreement before commissioning a professional-work evaluation.
Compare the approach
Mercor review for expert AI training work
Read how an individual expert role differs from licensing an employer or client’s work product.
Related industry examples
Industry guide · NAICS 541618
Utilities management consulting metric scope data for AI
A utility operations dashboard may change which service area or customers a summary covers.
Industry guide · NAICS 541612
HR consulting job analysis and competency evidence for AI
Job analysis connects tasks and required competencies.
Industry guide · NAICS 541614
Logistics consulting process-event and elapsed time data for AI
A process map can show goods waiting at a dock before handling starts.