Industry field guide
Gypsum lot and shipment reporting data for AI
A shipment record can show what left a site without identifying all material recorded for the period.
- Sector
- Mining, oil and gas
- 2022 NAICS
- 212390
- Practice pack
- Example and answer key (JSON)
- Updated
What this guide tests
How much outbound material is directly linked to G-A, and can the packet establish G-A's total production or ending inventory?
See the specimen and fields · Work through the fictional records
Task and source context
A shipment record can show what left a site without identifying all material recorded for the period. USGS publishes gypsum statistics and commodity information. A nonmetallic minerals operator can test whether an assistant reports the right level of evidence using artificial values and two independent sources. USGS gypsum statistics and information
Invent a report with a production summary and two outbound records. Mark one shipment as linked to an individual lot, and leave the other represented only in a combined total. Ask which quantity can be attributed, what the totals cover, and which record would be needed for a stronger claim.
Keep production, pricing, customer records, operating methods, site locations and equipment details private. Use a synthetic example with no shipping or operational decision.
Industry research
The U.S. Census Bureau’s industry definitions establish which activities these codes cover. The workflow sources in this guide describe the task or record type. Fiund’s pilot below uses fictional material to test a specific decision within that scope.
212390 · Other Nonmetallic Mineral Mining and Quarrying
This industry comprises establishments primarily engaged in developing the mine site, mining, and/or milling or otherwise beneficiating (i.e., preparing) nonmetallic minerals (except coal, stone, sand, gravel, clay, and ceramic and refractory minerals). Drylake brine operations are included in this industry, as well as establishments engaged in producing the specified minerals from underground and open pit mines.
Build a pilot sample
Set up this pilot
Create a mock outbound gypsum ledger with two linked tickets and one anonymous movement. Sum attributed shipments and keep production and inventory beyond the covered period open.
Prepare the test packets
- Start with the worked case. Use the fictional record types below as a guide to the source files you need. Give each packet a stable ID and save its source versions with it.
- Change one fact. Make one packet with enough evidence to answer the question and one where the evidence points to a different answer. Keep the other fields fixed so a reviewer can tell what changed.
- Remove the decisive evidence. Give the reviewer a third packet with a plausible near-match in its place. Have them write what can still be established and what evidence would resolve the rest.
Fields the reviewer needs
- Reporting period and quantity type
- Separates production from outbound movement.
- Ticket-to-lot link
- Identifies the amount actually attributable to G-A.
- Unassigned shipment quantity
- Preserves a gap instead of forcing a lot match.
- Inventory coverage
- Shows what additional records a balance calculation would need.
Use Plan a sample of business data for AI to turn the specimen into a brief with a defined task, source and review owner.
Fictional exercise
A period shipment total cannot be allocated to an unnamed lot
A fictional gypsum ledger uses practice mass units. It distinguishes period production from outbound shipments and deliberately leaves one shipment's lot identity unresolved.
| Record ID | Source | What it records |
|---|---|---|
| GY1 | Monthly summary | Period M records 30 practice units produced and 18 outbound. |
| GY2 | Outbound ticket OUT-1 | 7 units shipped from lot G-A during M. |
| GY3 | Outbound ticket OUT-2 | 11 units shipped during M; lot identity absent. No opening or closing inventory is supplied. |
Question for the model. How much outbound material is directly linked to G-A, and can the packet establish G-A's total production or ending inventory?
Show the reference answer
GY2 directly links 7 outbound units to G-A. GY1 and GY3 reconcile the period's total outbound quantity as 7+11=18, but the unassigned 11 cannot be attributed to G-A. The 30-unit production summary covers period M rather than that lot. Without lot-level production and inventory records, G-A's total production and ending balance remain unknown.
How to check the result
Ask for the answer, the record IDs that support it and any fact the evidence leaves unresolved. Have a reviewer compare the response against the reference before deciding whether the sample is ready to expand.
Errors to flag in this case
- Assigning all period production or both outbound tickets to the only named lot.
- Calling production minus shipments the ending inventory despite missing opening stock and lot scope.
Change the inputs and run it again
Provide a corrected OUT-2 assigning it to G-B and an opening balance for G-A, but no G-A production record. Require the system to update attribution while still declining to calculate an unsupported closing balance.
Score the decision and the evidence separately
Save the reviewer’s expected answer, supporting record IDs and unresolved fields in a separate answer key. Score the model on the decision, its citations and its handling of the deliberate gap. A correct answer citing a different case counts as an evidence error.
Before expanding collection, have a second reviewer run the same checks on the held-out packet. Keep related versions, views and exports of the same case together so they stay on one side of the training and evaluation split.
Check permission and scope
Use invented summaries and quantities. Exclude real production volumes, customers, shipment destinations, prices, operating methods and site information.
Exclude non-public reserve estimates, facility access details and proprietary extraction methods.
Describe an authorized archive through Fiund’s existing-data assessment, or describe a new capture capability through the collection brief. The contributor agreement covers the terms for participation.
Sources and further reading
Resources for this workflow
Company and program reviews
Use these reviews to compare sourcing, capture or evaluation approaches. Confirm the applicable program, accepted sources and terms with the provider.
Compare the approach
Scale AI review: data partnerships, Outlier and buyer services
Read how the company frames energy and utility data partnerships and what it asks of established operators.
Compare the approach
Sapien review: dataset quality review and expert checks
Compare expert quality review if a pilot needs independent checks of evidence and labels.
Related industry examples
Industry guide · NAICS 212321
Construction sand and gravel fraction records for AI
A result for a separated fraction can appear beside a record for a combined sample.
Industry guide · NAICS 212323
Clay sample preparation records for AI evaluation
Two results may describe the same source material at different preparation stages.
Industry guide · NAICS 212313
Crushed granite stockpile transfer records for AI
A stockpile name can remain in a dispatch system after a material transfer.